Title: Critical Chain Analysis Using Project Management Software
Authors: Balakrishnan, Jaydeep
Keywords: Critical Chain;Project Scheduling;Resources;Activity Slacks;Buffer
Issue Date: 2009
Publisher: APICS
Citation: Balakrishnan, J. (2009). Critical chain analysis using project management software. Production and Inventory Management Journal, 45(1), 13-20. Retrieved from http://ezproxy.lib.ucalgary.ca/login?url=http://search.proquest.com/docview/199916784?accountid=9838
Abstract: Previously in this journal, Umble and Umble (2000) discussed Goldratt’s “critical chain” (Goldratt 1997) for project scheduling. In this article, we show that explicitly defining the critical chain in a resource constrained project schedule will help avoid errors in slack calculation. Because these slacks can help identify the feeding buffers in critical chain analysis and prepare the backward schedules for the activities, it is important to identify them correctly.
Description: Post print deposited 05/12/2016. Link to publisher's version http://ezproxy.lib.ucalgary.ca/login?url=http://search.proquest.com.ezproxy.lib.ucalgary.ca/docview/199916784?accountid=9838
URI: http://hdl.handle.net/1880/51198
ISSN: 08978336
Appears in Collections:Balakrishnan, Jaydeep

Files in This Item:
File Description SizeFormat 
PIMJ Critical chain Balakrishnan final 2009.docx138.14 kBMicrosoft WordView/Open


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.