Critical Chain Analysis Using Project Management Software
Accessioned
2016-05-12T16:19:07ZAvailable
2016-05-12T16:19:07ZIssued
2009Metadata
Show full item record
Abstract
Previously in this journal, Umble and Umble (2000) discussed Goldratt’s “critical chain” (Goldratt 1997) for project scheduling. In this article, we show that explicitly defining the critical chain in a resource constrained project schedule will help avoid errors in slack calculation. Because these slacks can help identify the feeding buffers in critical chain analysis and prepare the backward schedules for the activities, it is important to identify them correctly.Refereed